Why is Von King Park still under construction in 2021?


Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.


Project Timeline

Design

Start Date: September 2013

Projected Completion Date: July 2014

Completion Date: August 2016

Procurement

Start Date: August 2016

Projected Completion Date: May 2017

Completion Date: June 2017

Construction

Start Date: September 2017

Projected Completion Date: March 2019

Adjusted Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $6,516,000